The mudders have completed their job and the tilers came today. The local flooring company didn’t measure correctly, so the installers didn’t have enough to finish. It will be a week or so before the tile will be available since it needed to be ordered. Oh, well. What’s another week? Found out that we didn’t need the marble transitions that I ordered, so we won’t have to pay for those. It’s only a little but it’s something.

Last weekend was devoted to prepping and priming all the walls. I also started putting up the extruded polyurethane crown moulding last night. I will be buying three different styles/sizes. With any luck, that will all be done this weekend and a lot more painting as well. The weather will be nice so it will be good to throw open the windows to get fresh air. No rest for the weary…